‘Ofgem Aims to Expedite Wind and Solar Projects by Eliminating ‘Zombie’ Initiatives’

‘Ofgem Aims to Expedite Wind and Solar Projects by Eliminating ‘Zombie’ Initiatives’

The energy ⁤regulator ⁤is to introduce rules designed to kick out “zombie” wind and ‌solar farms from‍ the lengthy queue to connect to Great Britain’s electricity grid.

Ofgem hopes to speed up the process of⁢ hooking up new energy projects to the electricity network‌ in ⁤the face of⁢ a backlog‍ that is deterring investment‌ and Britain’s attempts to switch to clean energy.

At the‌ moment,‌ projects are connected to the grid on a⁢ first come, first served ⁢basis‌ – leaving some developers ⁣waiting ‌up to 15 years to produce power for the country’s homes and businesses.

UK subsidies for offshore⁤ windfarms likely to increase amid rising costsRead more

In certain cases, developers have ‍been granted a ​contract allowing them a grid connection for a location, but have not progressed the project, possibly with the aim of selling the connection on at a later date. The projects include onshore and offshore ⁣wind, solar ⁢farms and⁤ battery storage businesses, and the first terminations are expected next year.

The regulator said on Monday it would hand National Grid’s ⁢electricity⁤ system​ operator (ESO), which controls the process, the power to terminate projects that were not‍ progressing against‌ their specific milestones, ⁢including proof of funding⁤ or planning permission. It will⁤ apply to all projects with a connection date after November⁣ 2025.

The ESO has said ‍that between 60%‍ and 70% of projects in the⁢ queue “ultimately fail to materialise or connect”. The number of projects waiting in line rose from 600 in May to ‌1,000 by September.

The⁢ average time between requesting a‍ connection ‍and ‌being offered​ one has increased from 18 months in 2019-20 to five years in 2023.

Ofgem said that, if the current projects in ‍the‌ queue were all developed,⁢ it would generate 400 gigawatts (GW) of power, far outstripping the UK’s existing power⁤ capacity of about 65GW. However, more than 40% of that is in‌ held-up​ contracts with connection⁣ dates of 2030‍ or later; some are as late as 2037.

Eleanor Warburton, an Ofgem‍ director, said: “The transition⁤ to net zero demands urgent changes⁤ to the electricity connections system – or we cannot unlock investment, speed up‌ network build and accelerate new technology.

“This is a big step towards phasing out the ​first come, first ​served queueing‍ system. We want new power‍ on ⁣the grid as quickly as possible, so if‌ you’re ready, you ⁤can connect sooner.

“If⁤ you’re not ready and are blocking‍ the⁤ progress of others,‍ you’ll be removed‌ – you can’t‌ sit on the queue with no consequences.”

Julian Leslie, ‍the chief engineer​ and head of networks at the ESO, said: “We⁢ warmly​ welcome these new⁢ rules approved‌ by Ofgem enabling us to proactively terminate zombie projects in the connections​ queue.”

skip past ​newsletter promotion

Earlier⁤ this year,‍ National‍ Grid offered ‍an⁢ “amnesty” to developers to‌ allow them to get out of the queue ⁢for a grid connection with no financial penalty. Its⁣ chief executive, John Pettigrew,…

2023-11-13 10:34:45
Original from www.theguardian.com
⁤rnrn

Exit mobile version